Approval of Amendment #8 to the FY2016-25 Transportation Improvement Plan (5 minutes)
Aaron Cain, LPA Staff
Narrative
Amendment #8 to the FY2016-25 Transportation Improvement Plan includes a request from GoTriangle to introduce a new project, TG-5235, FY 2017 Capital-Cameras, for the purchase and installation of security cameras at the Regional Transit Center, Bus Operations and Maintenance Facility, and the Plaza Building. In addition, there are 12 project additions and three modifications from NCDOT. None of the projects initiated by DCHC members include changes in funding greater than $1M. A summary list and full report of the changes are included as attachments along with a resolution to be signed by the MPO Board Chair upon approval by the Board.
Board Action
TC Action: Recommended thde Board approve Amendment #6 to the FY2016-2025 TIP.